If you are planning a custom home anywhere in the DFW area, here is the honest answer up front: expect 3 to 6 months of design and permitting, then 12 to 14 months of construction. Call it 15 to 20 months from our first coffee to your move-in day. That is the real number behind our five-step build process, refined over 100+ custom homes since 1995, and most of our homes deliver within two weeks of the original target date.
The timeline question matters because it is where builders most often mislead people. A short number wins the contract; a long build loses the client's trust. So let me walk you through the actual months.
What Does the Full Timeline Look Like, Phase by Phase?
Our process runs through five steps: Consult, Design, Select, Build, Deliver. Here is how those steps map onto the calendar for a typical Open Prairie home:
| Phase | Months | What happens | What you are doing |
|---|---|---|---|
| Consult | Month 0 | Free 45-60 minute consultation, site walk, feasibility check, ballpark cost range | Talking through your vision, lot, and budget |
| Design | Months 1-4 | Schematic design with 2-4 revision rounds, structural engineering, MEP design, permit-ready documents | Reviewing plans, making layout decisions |
| Select | Months 3-6 | Showroom selections with real pricing, specifications written into the contract, cost locked before groundbreaking | Picking every finish with me beside you |
| Permitting | Months 4-6 | City or county filings, septic permitting on acreage, inspections scheduled | Mostly waiting, we handle the paperwork |
| Build | Months 6-18 | Foundation through finish-out, daily oversight, weekly walk-throughs | Attending one walk-through per week |
| Deliver | Final month | Punch list before closing, warranty in writing, move-in | Getting keys to a finished home |
Design and selections overlap on purpose. Picking finishes while the plans are still alive means we can price the home with real numbers, not allowances, before anything is signed.
What Happens During the 3 to 6 Months of Design and Permitting?
This is the phase impatient buyers want to rush, and it is the phase that determines whether the next 14 months go smoothly. The design work typically runs 4 to 8 percent of the build cost and covers schematic design, structural engineering for North Texas clay, and full construction documents.
Permitting time depends heavily on where you build. A lot inside city limits in Weatherford or Fort Worth goes through municipal plan review, which adds weeks compared to unincorporated land. Acreage in rural Parker County near Springtown or Peaster permits through the county, which is faster on the building side but adds septic permitting through Parker County Public Health. Neither path is bad. They are just different clocks, and a builder who has run both since 1995 knows how to start them early and in parallel.
What Does the 12 to 14 Month Construction Phase Look Like Month by Month?
Every home is different, but a typical Open Prairie build sequences roughly like this:
- Months 1-2: Site work and foundation. Pad, utilities, forms, plumbing rough-in under the slab, engineered foundation poured and cured. On acreage, add the well, septic, and driveway work. If the home has a basement, excavation and basement walls come first and add a month or so.
- Months 3-5: Framing and dry-in. The skeleton goes up, then roof decking, windows, and exterior wrap. This is the stretch most exposed to spring storms.
- Months 5-8: Mechanicals and masonry. Electrical, plumbing, and HVAC rough-in inside while stone and brick go up outside. Inspections at every milestone.
- Months 8-11: Insulation, drywall, and trim. The home goes from a structure to a house. Cabinets, interior doors, and millwork land here, which is why selections locked back in month four keep everything moving.
- Months 11-14: Finish-out. Countertops, tile, flooring, paint, fixtures, appliances, final grading and landscaping, then a full punch-list walk-through before closing, not after.
You are never guessing where things stand. I am on the job site daily and we walk the home together every week.
What Stretches a Custom Home Timeline in North Texas?
When a build blows past 18 months of construction, one of four things usually happened:
- Permits started late. Design finished before anyone filed anything, so the project sat still for two months that could have run in parallel.
- Weather with no cushion. North Texas spring storms will cost you days every year. A schedule with zero weather allowance is a schedule designed to be missed.
- Change orders after drywall. Decisions made late force trades back out of sequence. This is the most expensive kind of delay, and the no-allowance selection process exists specifically to prevent it.
- An overloaded builder. This is the big one. A builder juggling a dozen concurrent homes is really asking each client to wait in line for the same framers, the same trim carpenters, and the same superintendent's attention.
The U.S. Census Bureau's Characteristics of New Housing data tracks average time from permit to completion nationally, and contractor-built custom homes consistently run longer than production homes. The spread between a well-run custom schedule and a badly run one is measured in months, not weeks.
Why Does Capping Active Builds Keep Schedules Honest?
We take on only a few builds at a time, deliberately. That is not a boutique affectation; it is the scheduling mechanism itself. When your home is one of three instead of one of fifteen, your foundation pour does not wait behind someone else's, your questions get answered the same day, and the owner of the company personally sees your job site every day it is active.
That is why I can say most of our custom luxury homes deliver within two weeks of the target date we set at contract. The date is not a sales number. It is a commitment I am personally on the hook for, backed by a one-year workmanship, two-year systems, and ten-year structural warranty in writing.
Timeline and budget also travel together. Your construction loan draws interest the entire time the home is under construction, so a builder who controls the schedule is also protecting your carrying costs. If you are still working out the money side, my post on what it costs to build a custom home in Weatherford pairs well with this one.
What Should You Do Next?
- Work backward from your ideal move-in date. If you want to be in the home 20 months from now, the design conversation needs to start this season, not next year.
- Walk your land with a builder before you finalize anything. Site conditions set the schedule as much as the floor plan does. Schedule a free consultation or call me directly at (817) 736-6323.
- Ask any builder you interview two questions. How many homes are you building right now, and what percentage of your last ten homes delivered within a month of the promised date? The answers tell you more than any brochure.
A custom home takes real time to build correctly. The goal is not to shortcut the calendar. It is to set an honest date and then hit it, which is exactly what we have done across North Texas for 30 years.

